How Much Is Copper Concentrate Per Ton? The Pricing Formula, Worked Through
There is no single price per ton. There is a formula, and once you can run it, every offer becomes comparable.
· 6 min read
Why there is no headline price
Copper concentrate is not a finished product with a market price. It is an intermediate material whose value depends on how much copper it contains, how much of that copper a smelter will pay for, what the smelter charges to process it, and what deductions apply for moisture and impurities. Two lots described as "copper concentrate" can differ in value by a factor of two.
So when a buyer asks how much concentrate costs per ton, the useful answer is the formula rather than a number — because the number is only meaningful attached to a specific assay and a specific date.
The formula
The industry standard calculation, per dry metric tonne, is:
- Start with
- Payable Cu% × LME reference price
- Deduct
- Treatment charge (TC), quoted per dry metric tonne
- Deduct
- Refining charge (RC), quoted per pound of payable copper
- Deduct
- Penalties for deleterious elements above contract thresholds
- Add
- Credits for payable gold and silver, where present
Payable copper is not contained copper
A smelter never pays for 100% of the copper in the concentrate, because some is lost in processing. The payable proportion is normally around 96 to 97% of the assayed copper content, and it is a contract term rather than a physical constant — it is negotiated, and a lower payable percentage is a real cost even when the headline grade looks attractive.
This is the first place where offers stop being comparable. A 30% Cu concentrate at 96.5% payable is a different proposition from the same grade at 95% payable, and the difference does not appear anywhere in the product description.
Treatment and refining charges
TC and RC are what the smelter charges to turn concentrate into metal, and they are effectively the seller’s cost of access to processing capacity. TC is quoted in US dollars per dry metric tonne of concentrate; RC in US cents per pound of payable copper. They move with global smelting capacity and concentrate availability, tightening when smelters compete for feed and widening when concentrate is scarce.
For a buyer, the important point is that TC/RC must be stated explicitly. An offer that quotes a flat dollar figure per tonne without disclosing the payable percentage and the treatment terms has hidden the two variables that determine what you are actually paying.
Moisture and the dry metric tonne
Concentrate is shipped wet, typically at 6 to 10% moisture, but settlement is on dry weight. Moisture is determined at inspection and deducted from the shipped tonnage, so a 1,000 wet metric tonne shipment at 8% moisture settles as 920 dry metric tonnes.
Getting the basis wrong is one of the more common commercial errors on a first transaction. Always confirm whether a quoted price is per DMT or per WMT, and whether the moisture determination is by the loading inspector, the destination inspector, or an agreed umpire.
A worked example
Take a 28% Cu concentrate, 96.5% payable, with the LME at a given reference. Payable copper per dry tonne is 0.28 × 0.965, or roughly 0.270 tonnes of copper. That figure multiplied by the LME reference gives the gross value per dry metric tonne, from which TC per DMT and RC per payable pound are deducted, along with any arsenic or bismuth penalties, before adding precious-metal credits.
The point of running it is comparability. Once you can calculate the number yourself, an offer that will not disclose payable percentage, TC/RC and penalty thresholds is visibly incomplete rather than merely competitive.
Questions Buyers Ask
How much is copper concentrate per ton?
There is no fixed figure. Value per dry metric tonne is payable copper multiplied by the LME reference, minus treatment and refining charges and any penalties, plus precious-metal credits. A 25% Cu lot and a 40% Cu lot have very different values, and both move daily with the LME.
What is payable copper in a concentrate contract?
The proportion of the assayed copper content that the smelter pays for, normally around 96 to 97%. The remainder covers processing losses. It is a negotiated contract term, so it should be stated explicitly in any offer.
Is concentrate priced on wet or dry tonnes?
Dry metric tonnes. Moisture, typically 6 to 10%, is determined at inspection and deducted from shipped weight. Always confirm whether a quotation is DMT or WMT before comparing offers.
What are TC and RC charges?
Treatment charge, quoted per dry metric tonne of concentrate, and refining charge, quoted per pound of payable copper. Together they represent the smelter’s fee for converting concentrate into metal, and they move with global smelting capacity.